08.08.2023
Balfour Beatty VINCI delivers third huge HS2 bridge move in the West Midlands in July

Balfour Beatty VINCI delivers third huge HS2 bridge move in the West Midlands in July (Source: Balfour Beatty VINCI)
- 5,600 tonne bridge moved under the Coventry to Leamington railway 27 hours ahead of schedule
- This is the third giant bridge move in two weeks as HS2’s construction ramps up in the West Midlands
- Over 500 people delivered the three bridge operations, part of the 9,000 workforce building HS2 in the region
Balfour Beatty VINCI have worked around the clock to move HS2's huge 5,600 tonne bridge into place under the Coventry to Leamington Spa railway in Warwickshire. The operation to slide the 22 metres long and 11 metres wide bridge into position took 5.5 hours and was completed 27 hours ahead of schedule.
From the start of blockade on Saturday 29 July, 113 metres of the existing rail track and 188 rail sleepers were removed by the team, then 15,000 cubic metres of ground including hard sandstone material was excavated to create the space for the bridge to be moved into.
It was moved into place using five 3.8 tonne jacks on a sliding surface, designed by specialist civil and structural engineering company Freyssinet, which allowed the bridge to be jacked on a guiding raft slab over a distance of 47 metres.
It moved at around 9 meters per hour and took 5.5 hours to be moved into its final position at 03.30 on Monday 31 July. This innovative construction method allows the bridge to be moved in one movement, which dramatically reduces disruption for rail passengers.
In the following days, the team worked 24/7 backfilled around the structure and put the rail track back in place above it, ready for the railway to be re-opened at 08.30 on Sunday 6 August.
The structure will allow the high speed railway to pass underneath the existing Coventry to Leamington Spa line. In the short term it will also allow construction traffic to pass under this line, reducing the number of lorries on the public highways. The structure also features an adjoining access bridge for a nearby farmer, which will start construction shortly.
This is the third major bridge move undertaken by HS2 in the last two weeks, as construction ramps up on all the structures, including bridges and viaducts, where HS2 will intersect with existing railway lines and roads in the West Midlands.
On 17 July, a 6,200 tonne bridge was moved into place by an 840-wheeled transporter at Fulfen Wood near Lichfield under the existing West Coast Main Line. On 28 July, a 2,600 tonne bridge was also driven under the existing South Staffordshire freight railway line at nearby Streethay.
James Briggs, HS2’s Project Manager said: “The team have done a brilliant job moving this 5,600 tonne bridge way ahead of schedule, and I’d like to thank everyone for pulling together to deliver such an efficient and safe operation. The bridge was built on-site adjacent to the existing railway – an innovative approach which means it takes days, not months, to safely complete our works, keeping disruption to a minimum for rail passengers."
HS2’s civils contracts Balfour Beatty VINCI is delivering the construction work, and a Design JV of Mott MacDonald and Systra delivered the design.
Shamus Banaghan, Project Manager for Balfour Beatty VINCI (BBV) said: “I am particularly proud to work alongside such an experienced team, who have worked around the clock to successfully slide the bridge into position under the Coventry to Leamington Spa railway line. Over the last two and a half years through design development to implementation, we have remained focused on delivering this critical bridge move during the fixed Network Rail blockade. I would like to extend my thanks to everyone who has contributed to us achieving this latest feat of engineering ahead of schedule.”
HS2 Ltd works closely with Network Rail to plan for HS2 works which require access to the existing rail network. Wherever possible, work programmes are aligned, so HS2 works and Network Rail’s ongoing upgrade and maintenance works are delivered simultaneously.
John Emery, Senior Sponsor for Network Rail, said: “This is a fantastic milestone for HS2 who we have worked with closely to combine their major construction work with a project to strengthen a historic railway viaduct near Leamington Spa which will help to secure the future of this key route for passengers and freight services. I’d like to thank passengers for their patience this week.”
The Fulfen Wood bridge operation, completed on Monday 17 July, was the UK’s heaviest bridge drive to install an intersection bridge structure beneath the West Coast Main Line at Fulfen Wood near Lichfield.
The 56 metre long and 19 metre wide structure will allow Britain’s new high-speed railway to pass beneath the busy existing railway line, on its route going north of Birmingham Curzon Street Station up to Crewe.
The giant 6,200-tonne concrete structure, which was built adjacent to the WCML over the last six months, was slowly manoeuvred into place on self-propelled modular transporters. Specially designed for very heavy lifting, the 840-wheeled transporter with four carrier beams was controlled by a remote steering system.
On Friday 28 July, the Streethay bridge was driven into place under the South Staffordshire freight railway on the same self-propelled modular transporters (SPMTs) that were used for the Fulfen Wood drive, but with 344 wheels for the lighter 2,600 tonnes structure.
Source: Balfour Beatty







08.08.2023
Sika acquires Chema – a leading Mortar Manufacturer in Peru
Sika has agreed to acquire a leading manufacturer of tile setting materials operating under the umbrella brand Chema in Peru. The acquisition strengthens Sika’s position in the fast-growing mortar market and provides major cross-selling opportunities through increased presence in the distribution channel. In addition, it significantly extends Sika’s manufacturing footprint. In 2022, the business to be acquired generated sales of CHF 50 million.

07.08.2023
Changes in the Management Board of SMT Scharf AG - Hans Joachim Theiss is leaving the company
SMT Scharf AG (WKN: A3DRAE; ISIN: DE000A3DRAE2) hereby gives notice that Mr. Hans Joachim Theiß has informed the Supervisory Board that he will not be extending his contract, which ends on December 31, 2023,

07.08.2023
FRHN backstops from RINGSPANN score points as a cost-effective quality solution
Backstops in machines and systems prevent uncontrolled and dangerous reverse rotation of drive shafts against the direction of operation. Low-speed backstops in the FRHN series from RINGSPANN are specially designed for use in inclined conveyor belt systems, bucket elevators or pumps.

03.08.2023
River bed mapping with marine seismic
From smoke to rain and mud: Having recently returned from a geophysical survey close to the wildfires in Alberta, our geophysics crews were straight back out on the next job. For the last weeks they’ve been out on the Athabasca River collecting marine sub bottom profiling data to map sediments and bedrock to help in an engineering river crossing project.

03.11.2023
From first Ideas to Implementation – Satisfaction is guaranteed when we are enthusiastic about what we construct!
Enthusiasm about what we do when we build something is an important key to job satisfaction; communicating this to others, valuing people we deal with, and attracting skilled personnel in future gen...
03.11.2023
Brenner Base Tunnel: innovative Sandvik DT923i convinces in Blasting of the main Tunnels
In the Brenner Base Tunnel, the innovative DT923i tunnel drill rig from In the Brenner Base Tunnel, the innovative DT923i tunnel drill rig from Sandvik is in use for the first time in Central Europe...
03.11.2023
German Exploration Geologist in Search of Battery Metals on the other Side of the World
Konrad Behnke studied geology in Germany with a semester and internship abroad. He left his comfort zone during the corona pandemic – travelling first to Scandinavia. He has been working as an...
28.11.2023 - 30.11.2023
Resourcing Tomorrow 2023
12.12.2023 - 13.12.2023
2nd International Congress and Exhibition - Mining of Uzbekistan and Central Asia
14.12.2023 - 15.12.2023
MINING WORLD CONGRESS 2023
14.12.2023 - 15.12.2023
GEOTEC HANOI 2023 – The 5th International Conference on Geotechnics for Sustainable Infrastructure Development

World’s longest Railway Tunnel Project – supported by innovative Conveyor Digitalisation and reliable Engineering
17. October 2022 (1955 Clicks)
The consortium BTC Brennero Tunnel Construction and the Hosch Group jointly delivered on a world-class tunnelling project by combining excellent engineering with the innovative remote monitoring system Hoschiris Discover.


RAG-Technikchronik - Buch 1: Technikentwicklung und Forschung der RAG
27. December 2019 (12957 Clicks)
Das Buch 1 "Technikentwicklung und Forschung der RAG" behandelt zusammenfassend die Ergebnisse der Bücher 2 bis 6 und ergänzt um das Thema Lagerstätte aus dem Buch 7. Das Thema „Forschung und Entwicklung“ wird genauso behandelt, wie der Streckenausbau, die Entwicklung der Technikbereiche, die Bergwerksautomatisierung und die Unternehmensdigitalisierung.


27.11.2023 (236 Clicks)
Akobo Minerals celebrates historic milestone: hitting gold ore body at the Segele Mine